The Manhattan WMS Guide

What Manhattan’s warehouse management systems are, how they differ, and what it takes to implement them, from the team behind 80+ go-lives on ActiveWarehouse.

What is Manhattan WMS

Manhattan WMS is the warehouse management software from Manhattan Associates. It runs receiving, putaway, inventory, picking, packing and shipping in the distribution centers of retailers, wholesalers, manufacturers and 3PLs.

“Manhattan WMS” is also shorthand for several different products. Manhattan’s current WMS is ActiveWarehouse, part of Manhattan Active®, and many operations still run one of its earlier platforms: WMOS, SCALE or WMi. Which one a company runs shapes almost every decision that follows, from support to the path forward.

Bricz has implemented Manhattan since 2013, with 80+ go-lives on ActiveWarehouse. This guide shares what our Manhattan practice sees in the field.

What is MAWM

MAWM stands for Manhattan Active® Warehouse Management, the cloud-native WMS from Manhattan Associates. Bricz also calls it ActiveWarehouse. It is part of the Manhattan Active® platform and updates continuously, so there are no version upgrades to plan.

MAWM brings warehouse management, labor management, slotting and SCI reporting together on one platform, and it is where teams on WMOS, SCALE and WMi are heading.

What are the key features of Manhattan WMS

Manhattan Active® Warehouse Management covers the full distribution center on one platform. These are the capabilities Bricz implements most often.

Warehouse execution

Receiving, putaway, inventory control, picking, packing and shipping, run from one system across every site.

Labor management

Engineered labor standards, real-time productivity tracking, performance dashboards and incentive plan design.

Slotting optimization

Item velocity profiling, slot assignment and continuous re-slotting, so picks stay short and congestion stays low.

Yard management

Gate check-in, dock-door and appointment scheduling, and trailer pool management beyond the four walls.

Automation and robotics

Connections to goods-to-person systems, conveyors and AMRs, so the WMS directs people and machines together.

SCI reporting

Manhattan’s reporting layer for operational and management reports across the warehouse.

What does Manhattan WMS integrate with

A Manhattan WMS implementation connects the warehouse to your ERP, order management system, transportation management system and automation. Integration endpoints, methods and data object mappings are defined during design and built during configuration.

Manhattan Active® also covers order management and transportation management, so teams running ActiveOrder or ActiveTransportation share one cloud-native platform with the warehouse. On earlier platforms, Bricz integrated Jasco’s Manhattan SCALE WMS with TGW’s ASRS via IBM MQ.

For shipping, Bricz connects parcel, LTL, TL and intermodal carriers to ActiveTransportation through EDI 204, 214, 990 and 210 messages and REST APIs, with rate procurement, contract loading and real-time visibility feeds, so freight is booked and tracked from day one.

How Manhattan WMS is recognized

Manhattan Associates is recognized as a Leader in the Gartner Magic Quadrant for Warehouse Management Systems, year after year, for completeness of vision and ability to execute. Read the Gartner report.

The four Manhattan WMS platforms

These are very different systems. Teams running one of them know which it is; the differences matter most when planning what comes next.

ActiveWarehouse

Cloud-native

Manhattan Active® Warehouse Management (MAWM)

Manhattan’s current WMS and a leading cloud-native platform. It updates continuously, so there are no version upgrades to plan.

WMOS

On-premise enterprise

Warehouse Management for Open Systems

The long-running on-premise enterprise WMS behind many large distribution networks.

SCALE

Microsoft-based

Manhattan SCALE

A Microsoft-based WMS built for mid-sized businesses.

WMi

IBM i (AS/400)

Warehouse Management for IBM i

A WMS that runs on the IBM i-series, also known as AS/400.

Why companies move to MAWM

These are the reasons Bricz customers give for moving from WMOS, SCALE or WMi to Manhattan Active® Warehouse Management.

  • No more upgrades. Updates arrive continuously, and new functionality is included with the subscription.
  • Security without downtime. Aging on-premise infrastructure can’t always be patched. In the cloud, security patches and code updates need no downtime.
  • Lower infrastructure cost. No servers to buy, run and maintain.
  • One platform. Warehouse management, labor management, slotting and SCI reporting work together on one platform.
  • Scalability. Capacity follows system load, so the platform grows with the business.
  • Open APIs. An API-based design adds agility and makes integration and extension simpler.
  • Support. Older versions have shrinking pools of support resources.

Moving to ActiveWarehouse from an earlier Manhattan WMS

Each move to ActiveWarehouse has its own tooling, sequencing and risk profile. Here is where each earlier platform stands today and how Bricz approaches the migration.

WMOS → ActiveWarehouse

WMOS and ActiveWarehouse are both Manhattan's leading enterprise WMS, so while the underlying architecture differs, the terminology and capabilities align closely — teams running WMOS find a natural match, and your business logic, slotting rules, and labor standards translate rather than disappear as we modernize the workflows that have collected workarounds along the way.

Where it stands

  • Last data model designed ~2010; v2020 is the final generally available release
  • Oracle DBMS on Red Hat Linux; modifications built and maintained by Manhattan
  • All customers now on maintenance support

How Bricz migrates it

  1. Configuration inventory. We document your existing WMOS workflows, integrations, and device scripts as the migration baseline.
  2. Data extraction & mapping. We extract and validate your master and in-flight data against ActiveWarehouse before anything loads.
  3. Configuration & cutover. We build ActiveWarehouse to your translated processes, then run a phased, DC-by-DC go-live with hypercare.
Read the full WMOS to ActiveWarehouse guide

SCALE → ActiveWarehouse

SCALE's configurability accumulates over time — MOCA scripts, custom extensions, edge-case logic. We surface all of it first, then decide what to translate, replace, or retire before ActiveWarehouse design begins.

Where it stands

  • Targeted at the commercial segment; many customers hosted in Manhattan's Azure cloud
  • Microsoft-based architecture
  • New releases annually on-prem or quarterly in cloud

How Bricz migrates it

  1. Configuration audit. We inventory your full SCALE environment: scripts, integrations, and wave and labor rules.
  2. Translation & design. Each piece of custom logic gets a disposition — native config, replacement, or rebuild — driving the AW design.
  3. Migration & go-live. We migrate data at volume and run a site-by-site rollout, stabilizing each site before the next.
Read the full SCALE to ActiveWarehouse guide

WMi → ActiveWarehouse

WMi migrations are full platform replacements with no hybrid path. We treat that as a chance to shed accumulated customizations and rebuild on best practices, planning the hard cutover from week one.

Where it stands

  • Manhattan's first WMS (PkMS), with a data model completed ~2001
  • Runs on IBM i
  • Still released annually, but with limited new capabilities

How Bricz migrates it

  1. Process discovery. We run structured workshops to map undocumented WMi workflows before design begins.
  2. Data & integration rebuild. We extract and cleanse WMi data and rebuild EDI and flat-file interfaces as modern REST APIs.
  3. Clean-slate go-live. We configure ActiveWarehouse to current best practices and execute a rehearsed hard cutover with hypercare.

Who does what in a migration

The split of responsibilities is the same whichever system you are leaving. Manhattan owns the platform-side workstreams; Bricz and your team own everything around them.

Manhattan

  • Design translation and fit/gap analysis
  • Hardware analysis
  • Configuration migration
  • Labor Management — Productivity Tracking
  • Integration Migration (if using MIF)
  • Migration of Critical SCI Reports
  • Migration of required extensions
  • 4-wall Systems Integration Testing (SIT) & Continuous Workflow Validation (CWV)
  • Creation of End User Training materials

Bricz and your team

  • Program management over all integrated systems
  • Business process design decisions & sign-off
  • SOP creation
  • Master & transactional data cleansing and provisioning
  • Custom / non-MIF integration build & endpoint readiness
  • Creation of continuous improvement roadmap
  • SIT & UAT test case development & execution
  • End-user training delivery
  • Cutover planning, execution & go-live hypercare

How long a Manhattan WMS implementation takes

The first site sets the pace. How closely a business can follow a proven template, and how complex the facility is, decide most of the timeline.

  • Template-led sites can be live in as little as six months for the first site.
  • More complex facilities can take up to 18 months.
  • Every site after the first rolls out significantly faster, and sites can be brought live in parallel.

Who is on the project team

A first-site ActiveWarehouse project brings together the client, Bricz and Manhattan. These are the typical roles; sizes grow with the implementation.

RoleFromTypical size
Project managerClient, Bricz and ManhattanOne from each. Overall governance is led by the client or Bricz.
Solution architectBricz1
Design leadManhattan with BriczManhattan typically leads design sessions; Bricz supports with industry best practices.
Integration lead and developersClient1 lead plus 2–3 developers, depending on the size of the implementation
SCI reporting developersBricz2–3, typically offshore, depending on the number of reports
Testing leadBricz1, leading functional, SIT, UAT and day-in-the-life testing
TestersBricz and client2–3 each. Bricz runs the first round in development; the client runs the second in QA or pre-production.
Automation leadBricz and client1 from Bricz, 1 from client IT and 1 from client operations
Training leadBricz and client1 each
Inbound and outbound operations leadsClient1 each

Why Manhattan WMS implementations struggle

The same few problems sink most projects that go wrong. Here is what the Bricz Manhattan practice sees, and what it does about each.

What goes wrong

Treating a move to MAWM as an upgrade instead of a rip-and-replace, and underestimating the effort.

What Bricz does

Bricz plans a customer moving from an older version exactly like a new customer. Both are new implementations.

What goes wrong

Keeping operations as-is instead of adjusting SOPs to fit the platform’s functionality.

What Bricz does

Bricz pushes to reduce extensions and suggests small operational changes that deliver the same result.

What goes wrong

Too little testing, on timelines that are too short.

What Bricz does

When you think you have tested enough, test some more. Bricz sets realistic time for testing and defect resolution.

What goes wrong

Underestimating the integration effort.

What Bricz does

MAWM is a very open system, but the lift from a legacy version is significant. Bricz sets realistic timelines for all integration testing, from host interfaces to automation.

Common questions about Manhattan WMS

ActiveWarehouse (MAWM) is cloud-native and updates continuously, so there are no version upgrades to plan. WMOS is on-premise: its final release is out and every customer is now on maintenance support. SCALE runs on-premise with annual releases or in Manhattan’s Azure cloud with quarterly releases. Teams on WMOS, SCALE and WMi are moving to ActiveWarehouse.

Manhattan WMS runs the distribution centers of retailers, wholesalers, manufacturers and 3PLs. Bricz has delivered ActiveWarehouse across beverage, grocery and manufacturing operations.

MAWM adapts to system load as demand changes. It scales with the business rather than forcing the business to scale with the platform.

Manhattan releases new functionality every quarter. New features arrive in a lower environment switched off, and they stay switched off when the code reaches production, so each client decides whether and when to use them.

Bricz typically sees about half of WMOS modifications eliminated by functionality already in MAWM. More can usually be removed through changes to standard operating procedures.

Data quality and migration, integration, and organizational readiness. A cutover is also difficult to reverse once the new system is live, which is why testing and rehearsal matter.

Work with a Manhattan WMS partner

Bricz implements ActiveWarehouse and supports teams on WMOS, SCALE and WMi, from planning a first site to rolling out a network. Comparing partners? Use the Manhattan partner checklist.