What moving from Manhattan WMOS to ActiveWarehouse (MAWM) involves, from where WMOS stands today to how the migration runs.
By Sharon Bondhus, Manhattan Practice Lead at Bricz·Updated November 2026
Where Manhattan WMOS stands today
WMOS, Warehouse Management for Open Systems, is Manhattan’s long-running on-premise enterprise WMS. It still runs many large distribution networks, but its final release is out and every customer is now on maintenance support.
For WMOS teams, the path forward is ActiveWarehouse, Manhattan Active® Warehouse Management (MAWM). Because both are Manhattan’s enterprise WMS, the terminology and capabilities line up closely.
Last data model designed ~2010; v2020 is the final generally available release
Oracle DBMS on Red Hat Linux; modifications built and maintained by Manhattan
All customers now on maintenance support
Why WMOS teams move to MAWM
These are the reasons Bricz customers give for moving to Manhattan Active® Warehouse Management.
No more upgrades. Updates arrive continuously, and new functionality is included with the subscription.
Security without downtime. Aging on-premise infrastructure can’t always be patched. In the cloud, security patches and code updates need no downtime.
Lower infrastructure cost. No servers to buy, run and maintain.
One platform. Warehouse management, labor management, slotting and SCI reporting work together on one platform.
Scalability. Capacity follows system load, so the platform grows with the business.
Open APIs. An API-based design adds agility and makes integration and extension simpler.
Support. Older versions have shrinking pools of support resources.
How a WMOS to ActiveWarehouse migration works
A familiar match, migrated for what's next.
WMOS and ActiveWarehouse are both Manhattan's leading enterprise WMS, so while the underlying architecture differs, the terminology and capabilities align closely — teams running WMOS find a natural match, and your business logic, slotting rules, and labor standards translate rather than disappear as we modernize the workflows that have collected workarounds along the way.
How Bricz migrates it
Configuration inventory. We document your existing WMOS workflows, integrations, and device scripts as the migration baseline.
Data extraction & mapping. We extract and validate your master and in-flight data against ActiveWarehouse before anything loads.
Configuration & cutover. We build ActiveWarehouse to your translated processes, then run a phased, DC-by-DC go-live with hypercare.
Who does what
Manhattan owns the platform-side workstreams; Bricz and your team own everything around them.
Manhattan
Design translation and fit/gap analysis
Hardware analysis
Configuration migration
Labor Management — Productivity Tracking
Integration Migration (if using MIF)
Migration of Critical SCI Reports
Migration of required extensions
4-wall Systems Integration Testing (SIT) & Continuous Workflow Validation (CWV)
Creation of End User Training materials
Bricz and your team
Program management over all integrated systems
Business process design decisions & sign-off
SOP creation
Master & transactional data cleansing and provisioning
A move from WMOS is a new implementation, so the first site follows the same timeline as any ActiveWarehouse project.
Template-led first site
From 6 months
Complex facility
Up to 18 months
061218 months
Template-led sites can be live in as little as six months for the first site.
More complex facilities can take up to 18 months.
Every site after the first rolls out significantly faster, and sites can be brought live in parallel.
What to watch for
The same few problems derail most moves to MAWM. Here is what the Bricz Manhattan practice sees, and what it does about each.
What goes wrong
Treating a move to MAWM as an upgrade instead of a rip-and-replace, and underestimating the effort.
What Bricz does
Bricz plans a customer moving from an older version exactly like a new customer. Both are new implementations.
What goes wrong
Keeping operations as-is instead of adjusting SOPs to fit the platform’s functionality.
What Bricz does
Bricz pushes to reduce extensions and suggests small operational changes that deliver the same result.
What goes wrong
Too little testing, on timelines that are too short.
What Bricz does
When you think you have tested enough, test some more. Bricz sets realistic time for testing and defect resolution.
What goes wrong
Underestimating the integration effort.
What Bricz does
MAWM is a very open system, but the lift from a legacy version is significant. Bricz sets realistic timelines for all integration testing, from host interfaces to automation.
WMOS to MAWM questions
Bricz typically sees about half of WMOS modifications eliminated by functionality already in MAWM. More can usually be removed through changes to standard operating procedures.
No. Bricz plans a move from WMOS exactly like a new implementation. Treating it as an upgrade is the most common reason teams underestimate the effort.
Customers who can follow a template can be live in as little as six months for the first site, while more complex facilities can take up to 18 months. Later sites roll out significantly faster and can run in parallel.
WMOS v2020 is the final generally available release, and all WMOS customers are now on maintenance support.
Plan your move from WMOS
Bricz has delivered 120+ Manhattan implementations since 2013. For the bigger picture across every Manhattan platform, see the Manhattan WMS guide.